Aviation Car Wash LP Update

with No Comments

 

Construction Update

  • Currently finalizing building envelope construction, and anticipate fully insulated envelope by mid November
  • Vehicle conveyance system install complete
  • Majority of car wash equipment has been received/secured on-site and installation initiated
  • Bulk of equipment installation will continue with full envelope enclosure in November

Opening January 2022

  • Enmax transformer has been energized with power and gas to site which will aid in keeping our costs down with alleviating any need for internal propane heating
  • Internal framing and drywall is substantially complete
  • Project construction is over 70% complete to-date

  • Currently tracking for construction completion late December 2021, with operational opening date anticipated to be in January 2022
  • The project is still tracking to construction budget