Construction Update
- Currently finalizing building envelope construction, and anticipate fully insulated envelope by mid November
- Vehicle conveyance system install complete
- Majority of car wash equipment has been received/secured on-site and installation initiated
- Bulk of equipment installation will continue with full envelope enclosure in November
Opening January 2022
- Enmax transformer has been energized with power and gas to site which will aid in keeping our costs down with alleviating any need for internal propane heating
- Internal framing and drywall is substantially complete
- Project construction is over 70% complete to-date
- Currently tracking for construction completion late December 2021, with operational opening date anticipated to be in January 2022
- The project is still tracking to construction budget